NIT for “EPC contract package covering Design & Engineering services, Civil and Hydro-Mechanical works of Sunni Dam Hydroelectric Project (382 MW) located in Distt. Shimla and Mandi in Himachal Pradesh, India was issued by SJVN Ltd (A Joint Venture of Govt. of India and Govt. of HP) on 20.04.2021 with deadline for submission of bids being 21.06.2021. The deadline for submission of bids has now being extended to 30.07.2021(1300 Hrs.).

Essca Consulting provides end-to-end bid/tender management services and can help bidders in complete Tender services ranging from Risk Analysis to detailed cost estimate, construction methodology, scheduling, price discovery, searching of sub-contractors and JV partners and liaison. We have duly verified data bank of reliable, competent and qualified parties who can be associated as sub contractors for Design & Engineering, Construction Management and Hydro-mechanical Works. Our team of qualified and experienced professionals have vast hands on experience in power sector both in government as well as private sectors like SJVN Ltd, NHPC, CCL, CEA etc., We can meet strict time schedule and provide bill of quantity and cost estimation and all other particulars required for successful tendering. For business enquiry, you may contact on +91-7217773663 or email us at– contact@esscaconsulting.com

SJVN Limited, a Mini Ratna, Category-I and Schedule –‘A’ CPSE is a joint venture of the Government of India (GOI) and the Government of Himachal Pradesh (GOHP). Beginning with a single Project i.e., India’s largest 1500 MW Nathpa Jhakri Hydro Power Station in Himachal Pradesh, the Company has commissioned five projects totaling 2015.2 MW of installed capacity including wind and solar power. The present EPC tender for Sunni Dam HEP is live and offers good opportunity for those companies who want to diversify in hydro sector but do not have any experience of hydro/river valley projects. As per bid conditions, to get qualified, they can participate in association with sub-contractors and joint venture partners.

Salient Features of the Project, NIT and the Qualification Criteria stipulated is given below.

Date of issue of NIT 20-4-2021
Documents available for download On or before 29-07-2021 (12.00 Hrs)
Pre bid meeting 05.07.2021
Deadline for submission of bids 1. Online submission : 30.07.2021 (1300 Hrs.) 2. Offline submission: 09.08.2021 (1800 Hrs.)
Estimated Value INR 1115 Crore (approx.)
Price basis Lump Sum with price variation clause (PVC)
Bid Security To furnish Bid Security Declaration
Project Features:
1. Location Near Khaira Village in district Shimla, River Satluj with District Shimla falling on its Left bank and District Mandi on its Right bank
2. Access Project site located at about 50 Kms from Shimla. Nearest railhead at about 145 Kms at Kalka. Nearest Airport is at Shimla (70Kms from site).
3. Dam Height + 71m from river bed level, Length at the top = 178m
4. Spillway 6 Nos., Sluice type (Radial gates)
5. Diversion Tunnel Left bank, 10m dia, 670m length
6. Power House Underground
7. Install Capacity 382MW

 

Disclaimer: Essca Consulting LLP assumes no responsibility or liability for any errors or omissions in the content of the NIT or other information provided herein based on the NIT floated by project owner. The information contained herein is provided on an “as is” basis with no guarantees of completeness, accuracy, usefulness or timeliness.